June 20: The glass came in and the doors are finished! This week the painting process has begun. Everything has been taped off and primer is already drying in anticipation for the paint. 
See if you can spot some color samples in one of the photos for a sneak preview of the wall colors.

[…]

Continue Reading

Doors, paint, and more!

On June 17, 2017 By

June 16: We have doors! Drywall is being touched up before we begin painting next week! Floors and ceiling will be starting soon as well. Waiting on a part to be delivered for the cooler before it is finished being installed in the back part of the warehouse. Looking good so far!

[…]

Continue Reading

June 6: Things are moving about a week ahead of schedule as of right now! As you can see most of the sheetrock is already in place on the front wall and upstairs offices. We have a new cooler in the process of being installed! Next week we will be moving onto installing the […]

Continue Reading

May 30: The place is really starting to come together! Insulation went in on the front framework recently and as you can see the sheetrock is already in the process of going up! The crew was doing some cement work near the doors and the upstairs has insulation already in place.

[…]

Continue Reading

May 23: Wall framing spanning from floor to ceiling is in place, defining some of the spaces that will be used for warehousing food, offices, conference area and restrooms. This week’s photographs provide looks at the marketplace area and food warehouse.

Photos: Lisa Robinson Photography

 

Continue Reading

We have stairs!

On April 30, 2017 By

April 27: The first full week of construction at Community FoodBank is coming to a close, and work is already ahead of schedule. Offices on the first floor are completely framed in. A new stairway to the second floor is complete, and framing is nearly finished on a new upstairs office/work area, according […]

Continue Reading

APRIL 30, 2017 HOLLISTER – Construction started this week on a floor-to-ceiling renovation and re-imagining project at Community FoodBank of San Benito.

The $2.25 million project includes purchase of the building in 2016. The project is scheduled to be completed by mid-August.

When completed, Community FoodBank’s 1133 San Felipe Road home will offer shoppers […]

Continue Reading

Demolition

On April 24, 2017 By

April 17:  DEMOLITION!  We said goodbye to our old office and warehouse space and started swinging the sledge hammers. 

 

Continue Reading

Moving Day!

On April 11, 2017 By

April 3 – 9:  FoodBank staff and volunteers help to move everything out of the entire building, to completely turn it over to Jeff Nohr, Project Manager for Avila Construction.

Thank you to South Valley Community Church for your help in clearing the office space in preparation for the renovation! A special thanks specifically to […]

Continue Reading

Pre-construction meeting for FoodBank’s building renovation project held at Hollister City Hall. FoodBank staff and construction companies met to plan the next steps.
 